Temec Engineering Mining Civil Engineers - Engineering Firms Vancouver BC
  • Piping Installation
    Major Challenge: Seven pumps run while one was worked on
  • Piping Installation
    Supply and return headers arrangement improved for better operation access.
  • Piping Installation
    Major Challenge: Very complex piping configuration in a very tight space.
  • Piping Installation
    Bearing cooling water control stations brought together outside containment building for ease of operation access
Client:Client: Rio Tinto, Kitimat, BC

Kemano Hydroelectric Plant – Generator Cooling Water

The Kemano hydroelectric plant produces power for use in the reduction process at the Rio Tino Alcan smelter in Kitimat, as well as provides power for use by communities in central British Columbia.  The cooling water piping sytems feeding the eight generators and transformers at the Kemano Power House, in service since the original construction, had reached the end of their life and required a complete piping system replacement.

  • BUSINESS PROBLEM SOLVED

    The risk of financial losses from potential downtime in the event of generator and transformer cooling water line failure was avoided by a complete piping system replacement.
  • TECHNICAL PROBLEM SOLVED

    Replacement of the existing piping required efforts to ensure the piping isolation strategy utilizing worn valves would allow safe replacement of the piping during operation of all other generators. 
  • WHAT WE DID

    All design aspects required by the Rio Tinto project approval gate process were followed to efficiently obtain project approvals and meet the installation deadline.

    Cost benefit analyses were performed to determine the best solution for the piping and insulation replacement materials, considering material and installation cost, as well as maintenance costs, effectiveness, and lifespan.

    Process and Instrumentation Diagrams were developed based on our comprehensive audit of the existing generator cooling water system.  Creation of a 3D model of the powerhouse piping allowed for efficient generation of 2D drawings for use in development of fabrication drawings and installation.  Temec  recognizes that 3D modelling is a valuable means of communicating design aspects to our clients as well as an efficient design tool.

  • PROJECT LIFECYCLE SERVICES USED

    Opportunity
    Definition
    • Conceptual Design
    • Implementation Plan and Schedule
    • Cost Estimating
    Design
    • Mechanical & Piping Design
    • Procurement Assistance
    • Document Control
    • Installation Contracts
    Fabrication
    Construction
    Start Up
    On Line